TENTATIVE PROJECT SCHEDULE

  • All dates are approximate and subject to change*

    • Demolition

      • Now – June 5th: Heavy wrecking and hammering

      • Now – July 31st: Material processing, cleaning, and hauling

    • Earthwork and Support of Excavation

      • Now – Q4 2023: Excavation with some ongoing work to demolish existing foundation walls, footings, and caissons

    • Utility Work

      • Starts in Late-May

    • Deep Foundations

      • Starts in July – Q4 2023: Drill rig used to install deep foundations.

  • Vertical Construction Start - Q1 2024

  • Construction Completion - Q4 2026

 